| Achievements: |
November 2011 - July 2012
- As of July 2012, this project was documented as being fully complete
- Occupancy Certificate received 6/27/2012
- During April 2012, renovations were documented as ongoing; entrance doors were installed, financial office stations ordered, security company installed CCTVs and access control equipment
- During December 2011, renovations began; floors were pulled up, sheetrock installed, ceiling suspension materials purchased, cashier windows installed at all locations; Fusion Solution completed the IT and Telephone rough-in work. Tutu Par Mall provided clean-out services of the sewer lines
October 2010 - October 2011 - No project updates were received until June 2011 when the grant period was documented as being extended from 6/29/2011 - 6/30/2012
September 2009 - September 2010 - A contractor was selected in May 2010; the Letter to Proceed and contract was signed; checks issued
- During January 2010, project stakeholders were able to obtain a government permit, notice of federal interest, recording with Lt. Governor's office, lease for additional space, and an owner's agreement letter
- During November 2009, the dental space was documented as being fully complete. The drawings for the mall expansion were also completed and submitted
- During September 2009, the mobilization of dental space was documented as being 25% complete
|